Test Bank For Contemporary Project Management 3rd Edition Timothy Kloppenborg
Chapter 1 – Introduction to Project Management
TRUE/FALSE
- A project is a temporary endeavor undertaken to create a unique product, service or result.
ANS: T DIF: Easy REF: P. 4 OBJ: CPMT.KLOP.15.01.01
NAT: BUSPROG.CPMT.KLOP.15.03 KEY: Bloom’s: Knowledge
- A project is a lasting endeavor undertaken to maintain a reliable product or service.
ANS: F DIF: Easy REF: P. 4 OBJ: CPMT.KLOP.15.01.01
NAT: BUSPROG.CPMT.KLOP.15.03 KEY: Bloom’s: Comprehension
- Most projects are conducted with constraints on the amount of time and funding available to the project manager.
ANS: T DIF: Moderate REF: P. 10 OBJ: CPMT.KLOP.15.01.01
NAT: BUSPROG.CPMT.KLOP.15.03 KEY: Bloom’s: Comprehension
- Project plans and goals usually become more specific as early work is completed.
ANS: T DIF: Easy REF: P. 4 OBJ: CPMT.KLOP.15.01.02
NAT: BUSPROG.CPMT.KLOP.15.06 KEY: Bloom’s: Knowledge
- Operations consist of the ongoing work needed to ensure the organization continues to function effectively.
ANS: T DIF: Easy REF: P. 5 OBJ: CPMT.KLOP.15.01.01
NAT: BUSPROG.CPMT.KLOP.15.03 KEY: Bloom’s: Knowledge
- Customers may need to sacrifice expectations related to cost or schedule in order to realize their expectations for scope or quality.
ANS: T DIF: Challenging REF: P. 10 OBJ: CPMT.KLOP.15.01.01
NAT: BUSPROG.CPMT.KLOP.15.06 KEY: Bloom’s: Analysis
- An important factor used to determine the phases in a project life cycle are the control needs of the organization(s) involved in the project.
ANS: T DIF: Moderate REF: P. 6 OBJ: CPMT.KLOP.15.01.02
NAT: BUSPROG.CPMT.KLOP.15.03 KEY: Bloom’s: Comprehension
- Generally, project life cycle stages are designed so that the amount of money spent in each of the stages is nearly equivalent.
ANS: F DIF: Moderate REF: P. 6 OBJ: CPMT.KLOP.15.01.02
NAT: BUSPROG.CPMT.KLOP.15.06 KEY: Bloom’s: Comprehension
- Project customers can be either internal or external to the organization.
ANS: T DIF: Easy REF: P. 6 OBJ: CPMT.KLOP.15.01.02
NAT: BUSPROG.CPMT.KLOP.15.03 KEY: Bloom’s: Knowledge
- Different project life cycle models are used for different types of projects.
ANS: T DIF: Easy REF: P. 6 OBJ: CPMT.KLOP.15.01.02
NAT: BUSPROG.CPMT.KLOP.15.06 KEY: Bloom’s: Knowledge